Romania’s energy sector is poised to increasingly rely on hydro-power, wind, and solar energy. These renewable sources, however, are subject to the unpredictability of wind, sunlight, and drought conditions. This variability places significant pressure on the Transmission System Operator (CNTEE Transelectrica SA), which is tasked with ensuring the safety and stability of the National Electricity System. As investments in renewables grow, enhancing investments in peaking / grid balancing capacities becomes critical to address the strains faced by the Transmission System Operator.
NAVIOS Investment, a company specializing in large-scale energy production investments, has recognized the shortfall in grid balancing capacities in Romania. In response, the company initiated investments in this sector starting in 2022.
Clarke Energy Romania serves as the EPC contractor for two 20 MWel power plants developed by NAVIOS Investment. Located in Racari, Dâmbovița County, these projects are designed to provide grid balancing services to the National Energy System of Romania.
The first phase of this project is now fully operational and is managed by Energy Innovative Solutions S.R.L (EIS), a subsidiary of NAVIOS Investment.
The second phase of the project is currently progressing in Racari and is overseen by Restore Energy SRL, another entity within the NAVIOS Investment SRL portfolio.
Key information – Phase 1 |
|
Client: | Energy Innovative Solutions S.R.L |
Capacity: | 20.15 MW |
Location: | Răcari, Dâmbovița, România |
Industry: | Grid Balancing |
Commissioned | 2023 |
Installation by: | Clarke Energy |
Engine Type | 6 x INNIO Jenbacher JMS 620 GS N.LC – v.J02 |
Fuel Type | Natural Gas |
Key information – Phase 2 |
|
Client: | Energy Innovative Solutions S.R.L |
Capacity: | 20.15 MW |
Location: | Răcari, Dâmbovița, România |
Industry: | Grid Balancing |
Commissioned | Scheduled Summer 2024 |
Installation by: | Clarke Energy |
Engine Type | 6 x INNIO Jenbacher JMS 620 GS N.LC – v.J02 |
Fuel Type | Natural Gas |