Clarke Energy has successfully completed an innovative project for Urbaser Environnement SAS in Tarn, France. The municipal biogas treatment plant of TRIFYL – Syndicat Départemental d’Elimination des Déchets – produces biomethane for injection into the Terega gas network. This project, the second largest in the region, marks a significant milestone in waste recovery and renewable energy production.
..
The installation processes 1850 Nm³/h of biogas, of which 1000 Nm³/h are injected into the network. The equipment from Tecno Project Industriale (TPI), provided by Clarke Energy, allows for the efficient treatment, compression, separation, and injection of biomethane.
The success of the biomethane injection project at the TRIFYL plant highlights Clarke Energy’s leading position in the field of renewable energy and waste recovery. This installation paves the way for future projects and significantly contributes to sustainable energy solutions in France.
The Trifyl biomethane injection project offers several advantages:
– The recovery of organic waste into renewable energy
– The reduction of waste volume
– The production of local sustainable energy
– Clarke Energy’s contribution to the energy transition.
Key information |
|
Client: |
Urbaser Environnement SAS |
Capacity: |
Biogas: 1800Nm3/h Biomethane: 1000Nm3/h |
Location: |
Tarn, France |
Commissioning: |
Q3 2023 |
Manufacturer: |
TPI (Tecno Project Industrial) Groupe SIAD |
Technology: |
Membrane Evonik |
Gas Type: |
H (>97% CH4) |
Annual Capacity: |
95 GWh/an |
Installation: |
Clarke Energy |
Maintenance: |
Full contract |