By the end of 2015, Clarke Energy will install its 1000th MW in Bégard in the Côtes d’Armor (22), on a greenhouse site named “Les Reflets Presqu’île”. Eiffage Energie is the client and Clarke Energy will install the facility and maintain the engines.

The event will involve presentations and a site visit.

The site is currently under construction and will house an Jenbacher JMS 624 engine which will generate 4.4 MW. During the month of July the construction phases are:

  • Installation of piping: hot water
  • Installation of client networks
  • Installation of thermal recovery
  • Installation of the gas line
  • Installation of duct smoke and chimney connection

On 29th July 2015 the JMS 624 engine will be installed.

We will communicate the progress of the construction site in August’s newsletter.

Clarke Energy is the leader of cogeneration in France with over 500 installed engines and more than 130 employees. We have a strong experience on a wide range of gas applications. The values ​​that made our success are:  quality, reliability, integrity and responsibility.

Find A News Article

Generic filters
Exact matches only

Find by Category

Any Further Questions?

If you have any technical questions that need answering, would like to arrange to speak to a sales advisor or book a feasibility study.